Saturday, August 27, 2011

Keel Laying Day

Throwing a party with some friends. Pics to follow. Standby.....



Friday, August 19, 2011

Just a half day in the shed.....

My buddy Andrew will be here tomorrow to help me hang the rest of the forms. This morning I got the transom form up. It was too heavy for just one person to wrestle into position so I used my winch. It put a lot of stress on the vertical's so I have to re-plumb them tomorrow.


I also built myself a small bridge over the back end of the strongback. This will be the main thoroughfare to get around the boat. It also gets me at working height for the transom. There's a step on the far side.

More tomorrow... Carry on.

Thursday, August 18, 2011

A lil' slow getting started

but I ended up spending 7 hrs in the shed today. After checking my levels and diagonals on the strongback numerous times I got to setting up the verticals that'll support the forms.


Not being very patient I just had to throw Frame E up to see how it looked!


All that nice open space I created when I cleaned up the shed is now gone! It's going to be tight but I'll have 2' on the south side and 3' on the workbench side as well as 1 1/2' at the bow and 2' at the transom to get around the boat. It would be nice to have more but this will have to do.

All of the forms line up on the baseline (B/L) which are already carved into the forms by the CnC machine. The tricky part is getting the baseline marked on all the verticals. I've got a number of options for doing this, liquid level, spirit level or laser level. I bought this small laser level just for this purpose and decided to use it. I set it up on the centerline at the B/L level. The tripod is too short and it'd just be in the way anyways.


I'll double check with a liquid level but I'm sure this will work fine.

I had a few more "WTF have I gotten Myself into moments today" especially when I was lining up this shot!


Maybe it's the tight space but this is going to be a pretty big boat.

Hope to get the remainder of the forms up on Saturday when my helper buddy is available. Standby....

Wednesday, August 17, 2011

I really wish I knew

what I was doing. I told ya I make most of this up as I go along. This strongback thing isn't any different. It's supposed to be simple ladder frame to hold the uprights that will hold the forms in position. Ok, well there's a picture in the instructions and plenty online but it still baffles me a bit. It's a good thing I don't build houses for a living!

I figured I had better start out plumb with my first post.


Pretty simple. Ok, all 10 of these are at different heights and have to be leveled individually, that's one of the downsides to working directly on the ground. There are times I wish I had poored a concrete pad to work on.

The next step was getting the second post square and plumb at the same time in relation to the first post.


My poor lil' laser level doesn't have 'nuff laserin' power to be visible in the daylight so I'll go out tonight after it gets dark and see how I did with just the long spirit level.


This is as far as I got before the temp climbed to over 34 degs C (about 94 F) and I had to bug out for the afternoon.


Hopefully tomorrow I'll get this thing finished and can start setting up the forms. I did make a few mistakes but I blame them on the supervisor falling down on the job today.


That's it for now. Time to cool down a bit.